Cisa Test QuestionsThe emergency exit
door is blocked. 07. Which of the next alternatives BEST enables statistics
owners to well classify statistics? Understanding of technical controls that
shield statistics Training on organizational rules and necessities Use of an
automated statistics leak prevention (DLP) tool Understanding which people need
to get right of entry to the statistics 08. A test that is executed at the same
time as a tool is withinside the development phase is: A sociability test A
functionality test A load test A unit test 09. An IS auditor is assigned to
audit a software program application development project, it truly is extra
than 80 percent complete, but has already overrun time through manner of way of
10 percent and expenses through manner of way of 25 percent. Which of the next
movements have to the IS auditor take? Report that the organisation does now
now no longer have effective project manipulate. Recommend the project manager
be changed. Review the IT governance form. Review the conduct of the project
and the business enterprise case. 10. An organisation’s risk urge for meals is
BEST installation through manner of way of: the steering committee. safety manipulate.
the audit committee. the chief prison officer.